Engineered Heavy Lifting Expertise Key to Taiwan’s Ambitious Offshore Wind Projects

Ørsted Taiwan, part of the world’s largest offshore wind company Ørsted, has selected Mammoet-Giant Taiwan, a joint venture between Mammoet, the engineered heavy lifting and transport specialist, and Taiwanese Giant Heavy Machinery Services - to provide essential support for the 920 MW Greater Changhua 2b and 4 offshore wind farms in Taiwan.

This remarkable offshore wind farm development is playing a crucial role in Taiwan's green energy targets, as it aims to achieve 5.7 GW of offshore wind power capacity by 2025.

This significant award builds upon Mammoet-Giant’s consistent success in Taiwan, where they have played pivotal roles in local offshore wind farm projects since the inception of offshore wind there in 2017. The JV has been entrusted with the marshalling and lifting activities for 66 suction bucket jackets.

2 Image 4Image credit: Mammoet

Drawing on their expertise in marshaling services, a pool of specialist heavy lifting and transport equipment, and dedicated personnel, Mammoet-Giant will deliver a comprehensive turnkey service for the project, from initial planning to execution, ensuring the jackets get into the water faster. By managing the complete quayside scope with meticulous planning and execution, the company will reduce interfaces, minimize project risks and ensure high levels of utilization with minimal disruption to port facilities.

3MammoetMammoet’s PTC200-DS ring crane was deployed at the Greater Changhua 1 and 2a offshore wind farms in 2022. Credit: Mammoet

To handle the quayside operations, Mammoet has selected its 5,000 t capacity SK 350 ring crane. Renowned for its exceptional lifting capabilities with a great reach, this powerful crane will be instrumental in achieving the project's objectives.

Operating from a single location, the SK350 will lift the 2,500 t suction bucket jackets directly from deck carriers to the quayside and after temporary storage on site, onto deck carriers ferrying the jackets to the installation vessel in the field. This methodology will eliminate the need for vessel repositioning during offloading and loading operations.

The crane’s design enables it to operate in the region’s high wind speeds, mitigating schedule risks and optimizing loading speeds. This reduces vessel turnaround times at the port to a minimum, resulting in multiple cost reductions and further schedule optimization.

Offshore Source Logo

Offshore Source keeps you updated with relevant information concerning the Offshore Energy Sector.

Any views or opinions represented on this website belong solely to the author and do not represent those of the people, institutions or organizations that Offshore Source or collaborators may or may not have been associated with in a professional or personal capacity, unless explicitly stated.

Corporate Offices

Technology Systems Corporation
8502 SW Kansas Ave
Stuart, FL 34997

info@tscpublishing.com